backport | [Openbravo ERP] 08. Project and service management | minor | always | 2008-12-18 17:49 | 2009-03-03 17:16 | |||
Reporter | pnuding | View Status | public | |||||
Assigned To | Hennadzi | |||||||
Priority | normal | Resolution | fixed | Fixed in Version | ||||
Status | closed | Fix in branch | 2.40 | Fixed in SCM revision | 11487 | |||
Projection | none | ETA | none | Target Version | ||||
OS | Any | Database | Any | Java version | ||||
OS Version | OB University Platform | Database version | Ant version | |||||
Product Version | 2.40 | SCM revision | ||||||
Review Assigned To | ||||||||
Web browser | ||||||||
Modules | Core | |||||||
Regression level | ||||||||
Regression date | ||||||||
Regression introduced in release | ||||||||
Regression introduced by commit | ||||||||
Triggers an Emergency Pack | No | |||||||
Summary | 0006658: Price for product in multi-phase project taken from wrong price list version | |||||||
Description | In Project and Service Management, the selected price list version is not respected when adding a product to a multiphase project phase or task. The system always uses the newest price list version, no matter what was selected. | |||||||
Steps To Reproduce | When doing the final exercise of the BFT on the OB University Platform (2.40) I noticed the following: I have created a multiphase project in Project and Service Management, now I select a product for a phase or for tasks within a phase. I have several price list versions, among them "Sales 2006 - EUR" which I want to use, where this product costs 2000 Euro, but there is also a newer "Sales 2008 - EUR" list created later where it costs 2400. I click to pop up the product selector, select the "Sales 2006 - EUR" price list version and click search. In the list of results I see the "Consulting Service" product I want to use with the correct applied price of 2000 Euro, I click to select it and click OK. The product now appears with the wrong list price of 2400 Euro in my phase. This is the price from the "Sales 2008 - EUR". It is taken no matter what I select. For comparison I tried adding the same product in a Sales Order, and there it correctly uses the price from the chosen price list, so this seems specific to Project and service management. | |||||||
Tags | comsup_sprint3 | |||||||
Attached Files | ||||||||
Relationships [ Relation Graph ] [ Dependency Graph ] | ||||||||
|
Notes | |
(0011659) svnbot (reporter) 2008-12-22 14:43 |
Repository: openbravo Revision: 11487 Author: hennadzi Date: 2008-12-22 14:43:42 +0100 (Mon, 22 Dec 2008) Bug fixed 0006658: Price for product in multi-phase project taken from wrong price list version --- U branches/r2.40/src/org/openbravo/erpCommon/ad_callouts/SE_ProjectLine_Value.java --- https://dev.openbravo.com/websvn/openbravo/?rev=11487&sc=1 [^] |
Issue History | |||
Date Modified | Username | Field | Change |
2008-12-18 17:49 | rafaroda | New Issue | |
2008-12-18 17:49 | rafaroda | Assigned To | => Dowid |
2008-12-18 17:49 | rafaroda | Status | new => scheduled |
2008-12-19 16:23 | PavelPonomarev | Assigned To | Dowid => Hennadzi |
2008-12-22 14:43 | svnbot | Checkin | |
2008-12-22 14:43 | svnbot | Note Added: 0011659 | |
2008-12-22 14:43 | svnbot | Status | scheduled => resolved |
2008-12-22 14:43 | svnbot | Resolution | open => fixed |
2008-12-22 14:43 | svnbot | svn_revision | => 11487 |
2008-12-23 10:22 | Hennadzi | Tag Attached: comsup_sprint3 | |
2008-12-23 10:22 | Hennadzi | Tag Attached: multi-org | |
2008-12-23 10:24 | Hennadzi | Tag Detached: multi-org | |
2009-03-03 17:16 | psarobe | Status | resolved => closed |