defect[Openbravo ERP] 09. Financial managementcriticalalways2012-10-11 22:522012-10-14 14:03
ReporterpjuvaraView Statuspublic 
Assigned Todmiguelez 
PriorityimmediateResolutionunable to reproduceFixed in Version
StatusclosedFix in branchFixed in SCM revision
ProjectionnoneETAnoneTarget Version
OSAnyDatabaseAnyJava version
OS VersionDatabase versionAnt version
Product Version3.0MP15.1SCM revision 
Review Assigned Toeduardo_Argal
Web browser
ModulesCore
Regression level
Regression date
Regression introduced in release
Regression introduced by commit
Triggers an Emergency PackNo
Summary

0021924: Balance sheet does not work when dates are expressed in MM-DD-YYYY

DescriptionThis is a regression.

Customer upgraded production environment from MP12.1 to MP15.1. After upgrade, the Balance Sheet & P&L report does not work anymore.

The customer is located in the USA and has the system configured with date format MM-DD-YYYY.

When you submit the report with date for example 09-30-2012 (balance sheet as of 30-SEP-2012), all the figures in the balance sheet come out to zero.

The data is correct. If you run the report without specifying a date, it works (it correctly shows figures as of the end of the year) but if you specify a date it does not.

This was working in MP12.1 and it no longer works in MP15.1, so it is a regression.
Steps To ReproduceSet date format to MM-DD-YYYY.
Submit the balance sheet as of a particular date.
TagsCoworking
Attached Filespng file icon Openbravo - Trial Balance Report - Wrong.png [^] (137,987 bytes) 2012-10-13 03:49


png file icon Openbravo - Trial Balance Report-Correct.png [^] (140,298 bytes) 2012-10-13 03:50

- Relationships Relation Graph ] Dependency Graph ]

-  Notes
(0053328)
pjuvara (reporter)
2012-10-13 03:49

The issue appears to be more complex than what originally reported.

If you run the Balance Sheet report as of 09-29-2012 (29 SEP 2012), it works fine (or at least it shows something); if you run it on 09-30-2012, it is empty.

The records in FACT_ACCT do not justify this behavior, so this is a reporting issue, not a data issue.

To validate what is going on, I run the Trial Balance in production. You can see in attachment two outputs, one from 01-SEP-2012 to 29-SEP-2012 (this is correct) and one from 01-SEP-2012 to 30-SEP-2012 (which does not return any data).

It is clear that for some reason the system interprets 30-SEP-2012 incorrectly when it is specified as 09-30-2012.

See screenshot attached.
(0053340)
eduardo_Argal (developer)
2012-10-14 14:03

Unable to reproduce. It is working fine

- Issue History
Date Modified Username Field Change
2012-10-11 22:52 pjuvara New Issue
2012-10-11 22:52 pjuvara Assigned To => dmiguelez
2012-10-11 22:52 pjuvara Modules => Core
2012-10-11 22:52 pjuvara Tag Attached: Coworking
2012-10-13 03:49 pjuvara Note Added: 0053328
2012-10-13 03:49 pjuvara File Added: Openbravo - Trial Balance Report - Wrong.png
2012-10-13 03:50 pjuvara File Added: Openbravo - Trial Balance Report-Correct.png
2012-10-14 14:03 eduardo_Argal Review Assigned To => eduardo_Argal
2012-10-14 14:03 eduardo_Argal Note Added: 0053340
2012-10-14 14:03 eduardo_Argal Status new => closed
2012-10-14 14:03 eduardo_Argal Resolution open => unable to reproduce