Anonymous | Login
Project:
RSS
  
News | My View | View Issues | Roadmap | Summary

View Issue DetailsJump to Notes ] Issue History ] Print ]
ID
0007389
TypeCategorySeverityReproducibilityDate SubmittedLast Update
feature request[Openbravo ERP] 04. Warehouse managementmajorhave not tried2009-02-05 13:202012-07-30 16:55
ReporterjtarbalView Statuspublic 
Assigned Togorkaion 
PrioritynormalResolutionfixedFixed in Version3.0MP13
StatusclosedFix in branchpiFixed in SCM revision
ProjectionnoneETAnoneTarget Version
OSAnyDatabaseAnyJava version
OS VersionDatabase versionAnt version
Product VersionSCM revision 
Review Assigned To
Web browser
ModulesCore
Regression level
Regression date
Regression introduced in release
Regression introduced by commit
Triggers an Emergency PackNo
Summary

0007389: Automatic execution of stock valuation process

DescriptionCurrently, the stock valuation processes have to be executed manually by the user. However, it would be great if these processes would be executed automatically by the system when specific events occur.

For purchased materials, the "Calculate average cost" process should be executed when completing a Goods Receipt.

For produced goods, the "Calculate production costs" process should be executed when completing a Work Effort.
TagsNo tags attached.
Attached Files

- Relationships Relation Graph ] Dependency Graph ]
related to feature request 0003465 closedgorkaion Automatize the AverageCost in Goods Receipts 

-  Notes
(0013553)
jtarbal (reporter)
2009-02-17 09:51

This feature is absolutely necessary when posting the "Goods Receipts" and "Goods Shipments" documents into the accounting as the amounts in the corresponding accounting entries depend on the stock value. Thus, as the stock value is only updated when executing, manually, the stock valuation processes, in order to have the accounting correct, the user should execute manually this process after each reception of goods.

As a conclusion, this feature is needed in all industries where the "Goods Receipts" and "Goods Shipments" need to be posted into the accounting.
(0050998)
gorkaion (developer)
2012-07-30 16:55

new cost engine is processed by an scheduled background process

- Issue History
Date Modified Username Field Change
2009-02-05 13:20 jtarbal New Issue
2009-02-05 13:20 jtarbal Assigned To => rafaroda
2009-02-05 13:20 jtarbal sf_bug_id 0 => 2568110
2009-02-11 11:50 rafaroda Assigned To rafaroda => pjuvara
2009-02-17 09:51 jtarbal Note Added: 0013553
2011-02-04 09:15 jpabloae Assigned To pjuvara => rmorley
2011-07-20 05:56 eintelau Issue Monitored: eintelau
2012-02-01 17:32 dmitry_mezentsev Relationship added related to 0003465
2012-07-30 16:54 gorkaion Status new => scheduled
2012-07-30 16:54 gorkaion Assigned To rmorley => gorkaion
2012-07-30 16:54 gorkaion fix_in_branch => pi
2012-07-30 16:55 gorkaion Note Added: 0050998
2012-07-30 16:55 gorkaion Status scheduled => closed
2012-07-30 16:55 gorkaion Resolution open => fixed
2012-07-30 16:55 gorkaion Fixed in Version => 3.0MP13