Project:
View Issue Details[ Jump to Notes ] | [ Issue History ] [ Print ] | |||||||
ID | ||||||||
0009631 | ||||||||
Type | Category | Severity | Reproducibility | Date Submitted | Last Update | |||
defect | [Openbravo ERP] 05. Production management | trivial | always | 2009-06-25 13:18 | 2011-10-28 18:49 | |||
Reporter | arunkumar | View Status | public | |||||
Assigned To | sathiyan | |||||||
Priority | low | Resolution | no change required | Fixed in Version | ||||
Status | closed | Fix in branch | pi | Fixed in SCM revision | ||||
Projection | none | ETA | none | Target Version | ||||
OS | Any | Database | Any | Java version | ||||
OS Version | Database version | Ant version | ||||||
Product Version | 2.50MP2 | SCM revision | ||||||
Review Assigned To | ||||||||
Web browser | ||||||||
Modules | Core | |||||||
Regression level | ||||||||
Regression date | ||||||||
Regression introduced in release | ||||||||
Regression introduced by commit | ||||||||
Triggers an Emergency Pack | No | |||||||
Summary | 0009631: Able to validate a work effort even if it is inactive | |||||||
Description | Create an work effort with the Active checkbox unchecked. Validate the work effort. Even if it is inactive we are able to validate it. | |||||||
Steps To Reproduce | Go to Production management->Transactions->Work Effort Click New and fill: Movement date= Current date Starting Time: 08:00:00, Ending time: 16:00:00 Move to Production Run tab and click new Select the "WR Phase" and verify: The fields "Required quantity", "Process unit" and "Conversion Rate" are filled based on the WR phase Fill Production Quantity=2 and save Click on button "Create Standards" The field "Cost centre used" is calculated well depending on you what configure on the Cost Centre. Move to Product tab and verify the product and their quantities. Move back to Work effort tab Click on button "Validate Work effort" Work effort has been validated successfully. | |||||||
Proposed Solution | Since we made the work effort as inactive, we will not be allowed to validate the work effort. | |||||||
Tags | 250MP2QAcylce | |||||||
Attached Files | ||||||||
Relationships [ Relation Graph ] [ Dependency Graph ] | |
Notes | |
(0042292) psarobe (manager) 2011-10-28 18:49 |
In 3.0 you cannot deactivate a work effort anymore since the field is not shown |
Issue History | |||
Date Modified | Username | Field | Change |
2009-06-25 13:18 | arunkumar | New Issue | |
2009-06-25 13:18 | arunkumar | Assigned To | => rafaroda |
2009-06-25 13:36 | arunkumar | Tag Attached: 250MP2QAcylce | |
2009-06-29 20:00 | psarobe | Status | new => scheduled |
2009-06-29 20:00 | psarobe | Assigned To | rafaroda => sathiyan |
2009-06-29 20:00 | psarobe | fix_in_branch | => pi |
2011-10-28 18:49 | psarobe | Note Added: 0042292 | |
2011-10-28 18:49 | psarobe | Status | scheduled => closed |
2011-10-28 18:49 | psarobe | Resolution | open => no change required |