Project:
View Issue Details[ Jump to Notes ] | [ Issue History ] [ Print ] | |||||||
ID | ||||||||
0004920 | ||||||||
Type | Category | Severity | Reproducibility | Date Submitted | Last Update | |||
backport | [Openbravo ERP] 05. Production management | minor | always | 2008-09-09 17:26 | 2009-03-26 18:45 | |||
Reporter | xplacesc | View Status | public | |||||
Assigned To | gorkaion | |||||||
Priority | normal | Resolution | fixed | Fixed in Version | 2.40MP4 | |||
Status | closed | Fix in branch | 2.40 | Fixed in SCM revision | c246fea63192 | |||
Projection | none | ETA | none | Target Version | ||||
OS | Windows | Database | Oracle | Java version | 1.5 | |||
OS Version | XP | Database version | 10g XE | Ant version | 1.7 | |||
Product Version | 2.40beta | SCM revision | ||||||
Review Assigned To | ||||||||
Web browser | ||||||||
Modules | Core | |||||||
Regression level | ||||||||
Regression date | ||||||||
Regression introduced in release | ||||||||
Regression introduced by commit | ||||||||
Triggers an Emergency Pack | No | |||||||
Summary | 0004920: Production MRP - Needed Product Quantity versus Work Requirement Quantity | |||||||
Description | When launching Production MRP, system works as follow: * calculates needed quantities (Q) * proposes work requirements Then with you launch work requirements, it creates a work requirement and fixes Quantity = Q. However, Q is product quantity but Quantity field in a Work Requirement, represents the number of times a work requirement will be executed, so it does not correspond exactly to produced products. | |||||||
Steps To Reproduce | * Create a Process Plan including just one only operation and a product P+ produced in a quantity of 2 * Set up Production MRP in order to obtain a proposed work requirement for example with a quantity of 10 * Launch work requirements in MRP * System will create a work requirement with a quantity field (in header) of 10, which really will mean 20 units of produced product, while needed quantity was 10 | |||||||
Tags | No tags attached. | |||||||
Attached Files | ||||||||
Relationships [ Relation Graph ] [ Dependency Graph ] | ||||||||
|
Notes | |
(0014581) hgbot (developer) 2009-03-11 15:02 |
Repository: erp/stable/2.40 Changeset: c246fea6319287b3b8a1411eddc9fb062554955f Author: Gorka Ion Damián <gorkaion.damian <at> openbravo.com> Date: Tue Mar 10 15:18:25 2009 +0100 URL: http://code.openbravo.com/erp/stable/2.40/rev/c246fea6319287b3b8a1411eddc9fb062554955f [^] Fixed bug 4920. The procedure to generate work requirements now calculates correctly the process plan quantity. --- M src-db/database/model/functions/MRP_WORKREQUIREMENT.xml --- |
(0015022) psarobe (manager) 2009-03-26 18:45 |
Steps to reproduce not clear |
Issue History | |||
Date Modified | Username | Field | Change |
2008-09-09 17:26 | anonymous | New Issue | |
2008-09-09 17:26 | anonymous | Assigned To | => gorkaion |
2008-09-09 17:26 | anonymous | Status | new => scheduled |
2008-09-09 17:26 | anonymous | fix_in_branch | => 2.40 |
2009-03-11 15:02 | hgbot | Checkin | |
2009-03-11 15:02 | hgbot | Note Added: 0014581 | |
2009-03-11 15:02 | hgbot | Status | scheduled => resolved |
2009-03-11 15:02 | hgbot | Resolution | open => fixed |
2009-03-11 15:02 | hgbot | Fixed in SCM revision | => http://code.openbravo.com/erp/stable/2.40/rev/c246fea6319287b3b8a1411eddc9fb062554955f [^] |
2009-03-24 11:01 | psarobe | Fixed in Version | => 2.40MP4 |
2009-03-26 18:45 | psarobe | Regression testing | => No |
2009-03-26 18:45 | psarobe | Status | resolved => closed |
2009-03-26 18:45 | psarobe | Note Added: 0015022 |
Copyright © 2000 - 2009 MantisBT Group |