feature request[Openbravo ERP] 05. Production managementminoralways2013-07-18 17:392013-07-18 17:39
ReporterVictorVillarView Statuspublic 
Assigned Todmiguelez 
PriorityhighResolutionopenFixed in Version
StatusnewFix in branchFixed in SCM revision
ProjectionnoneETAnoneTarget Version
OSAnyDatabaseAnyJava version
OS VersionDatabase versionAnt version
Product VersionpiSCM revision 
Review Assigned To
Web browser
ModulesCore
Regression level
Regression date
Regression introduced in release
Regression introduced by commit
Triggers an Emergency PackNo
Summary

0024375: to manage production on a made-to-order basis

Descriptionexample.
Customer buys nuts and storage them by the pound.
Products sold are packages on a presentation such as 1lb, 2lb, 14oz; etc

When a sales order for nuts 14oz package is entered, when the physical
shipment is done, the product is packed and shipped at the same time, so no
inventory is kept at 14oz presentation.
We need a functionality where at the moment that an order is entered, a
work order is created and completed to have the product available.
Information for the work order (such as lot numbers used during the packing
process) should be something that needs to be entered during the
packing/shipping process. Currently, it's complex to open a work
order, complete it and then process the goods shipments for this type of
transactions.
Steps To Reproduce
When a sales order for nuts 14oz package is entered, when the physical
shipment is done, the product is packed and shipped at the same time, so no
inventory is kept at 14oz presentation.
We need a functionality where at the moment that an order is entered, a
work order is created and completed to have the product available.
Information for the work order (such as lot numbers used during the packing
process) should be something that needs to be entered during the
packing/shipping process. Currently, it's complex to open a work
order, complete it and then process the goods shipments for this type of
transactions.
Proposed SolutionThere should be at least three improvements:
1.- When the user process the sales order, the new process should create the Work requirement (based on a process plan defined) and process it in order to create the Work Effort (the standards should be generated too). The user should validate the Work Effort to process it.
2.- This final validation should create the Goods Shipment associated.
TagsNo tags attached.
Attached Files

- Relationships Relation Graph ] Dependency Graph ]

-  Notes
There are no notes attached to this issue.

- Issue History
Date Modified Username Field Change
2013-07-18 17:39 VictorVillar New Issue
2013-07-18 17:39 VictorVillar Assigned To => dmiguelez
2013-07-18 17:39 VictorVillar Modules => Core
2013-07-18 17:39 VictorVillar Triggers an Emergency Pack => No
2013-07-18 17:39 VictorVillar Issue Monitored: networkb


Copyright © 2000 - 2009 MantisBT Group
Powered by Mantis Bugtracker