Project:
| View Issue Details[ Jump to Notes ] | [ Issue History ] [ Print ] | |||||||||||
| ID | ||||||||||||
| 0013431 | ||||||||||||
| Type | Category | Severity | Reproducibility | Date Submitted | Last Update | |||||||
| feature request | [Openbravo ERP] 06. Material requirement planning (MRP) | minor | always | 2010-05-25 12:56 | 2011-07-20 18:12 | |||||||
| Reporter | networkb | View Status | public | |||||||||
| Assigned To | jonalegriaesarte | |||||||||||
| Priority | high | Resolution | open | Fixed in Version | ||||||||
| Status | new | Fix in branch | Fixed in SCM revision | |||||||||
| Projection | none | ETA | none | Target Version | ||||||||
| OS | Any | Database | Any | Java version | ||||||||
| OS Version | Database version | Ant version | ||||||||||
| Product Version | 2.50MP17 | SCM revision | ||||||||||
| Merge Request Status | ||||||||||||
| Review Assigned To | ||||||||||||
| OBNetwork customer | OBPS | |||||||||||
| Web browser | ||||||||||||
| Modules | Core | |||||||||||
| Support ticket | ||||||||||||
| Regression level | ||||||||||||
| Regression date | ||||||||||||
| Regression introduced in release | ||||||||||||
| Regression introduced by commit | ||||||||||||
| Triggers an Emergency Pack | No | |||||||||||
| Summary | 0013431: You can not process a Manufacturing Plan | |||||||||||
| Description | You can not process a Manufacturing Plan if the product is marked as Production and Purchase but you can if only is marked as Production . | |||||||||||
| Steps To Reproduce | As Openbravo Admin go to Material Requirement (MRP) || Setup || Planning Method - Create a new record. Create a line for each Transaction Type. - Go to Material Requirement (MRP) || Setup || Planner - Create a new record. - go to Master Data Management || Product - Select Hammer and mark Production and Purchase. - Go to Product >> Org Specific - Select the Planning Method and the Planner created. - Go to Production Management || Transactions || Process Plan - Create a new record, go to Version. - Create a new record, go to Operation. - Create a new record, go to I/O Products - Create a new record: - Hamme, P+, Quantity:35 - Other product, P-, Quantity 45 - Go to Material Requirement (MRP) || Transactions || Manufacturing Plan - Create a new record: - Time Horizon:120 - Safety Lead Time: 2 - Planner: Planner created. - Product: Hammer. - Click 'Process Manufacturing Plan' - Realize that there are not lines. - Go to Product: Hammer. - Mark hammer only as Production. - Go to Material Requirement (MRP) || Transactions || Manufacturing Plan - Click 'Process Manufacturing Plan' - Realize that there are lines. | |||||||||||
| Tags | No tags attached. | |||||||||||
| Attached Files | ||||||||||||
Relationships [ Relation Graph ]
[ Dependency Graph ]
|
|
Issue History |
|||
| Date Modified | Username | Field | Change |
| 2010-05-25 12:56 | networkb | New Issue | |
| 2010-05-25 12:56 | networkb | Assigned To | => adrianromero |
| 2010-05-25 12:56 | networkb | OBNetwork customer | => Yes |
| 2011-06-03 10:59 | dalsasua | Assigned To | adrianromero => dalsasua |
| 2011-07-20 18:12 | dalsasua | Assigned To | dalsasua => jonalegriaesarte |