0006318: RFE: Purchase Order: Scheduled Delivery date for the line
Procurement Management || Transactions || Purchase Order || Header >> Lines

The scheduled delivery date for a line in a Purchase Order should be defaulting from the header.
Right now there is no coding about the behaviour, there is jsut a setup which sets it to @datepromised@

So what happens now is that if you enter a Purchase Order with a Scheduled Delivery date of today (December 2, 2008), when enter the first line, the Scheduled delivery date defaults to December 2, 2008 (from the header).

If I fill out a scheduled delivery date of December 10, 2008 on Line 1 and save.
Then when I enter a second line on the PO, the defaul scheduled delivery date appears as December 10, 2008 (like first line) instead of taking the value of December 2,2008 from the header.

This behaviour doesn't make any sense. The default should be taken from the header, not from the previously entered line.
The default should be taken from the header, not from the previously entered line.
ReleaseCandidate, Uservoice
Issue History
2008-12-02 12:04RenateNieuwkoopNew Issue
2008-12-02 12:04RenateNieuwkoopAssigned To => rafaroda
2008-12-02 12:04RenateNieuwkoopsf_bug_id0 => 2376761
2008-12-10 14:44rafarodaAssigned Torafaroda => pjuvara
2009-09-15 19:16pjuvaraTag Attached: ReleaseCandidate
2009-09-15 19:16pjuvaraTag Attached: Uservoice
2009-09-15 19:16pjuvaraStatusnew => acknowledged
2011-02-04 09:11jpabloaeAssigned Topjuvara => rmorley

There are no notes attached to this issue.