Notes |
|
(0012019)
|
AinhoaPagola
|
2009-01-09 12:12
(edited on: 2009-01-13 12:47) |
|
I can't reproduce this bug in 2.40. Can you verify the bug still exists and provide the steps to reproduce it?
|
|
|
(0012380)
|
RenateNieuwkoop
|
2009-01-20 11:05
|
|
Hi Ainhoa,
The strange thing is that you go to the created PO and you see that it is in Draft status, which looks normal. However, when you click the 'complete' button, it shown 'unlock', so it appears that the PO is locked and needs unlocking before you can actually complete the order.
I used the data in the training environment. So I had the product 'hammer'. You'll find the exercise in the Production module of the BFT training that you followed in Pamplona.
These are the data: stock of the hammer 985, 1000 safety stock
PO for 40x, SO for 350x
Then when you run the purchasing plan you get suggested POs and when you create them they are in 'draft' status, but locked (you find out when trying to complete the PO).
thanks
Renate |
|
|
|
Hi Renate.
I have verified that the issue still exists and will be fixed shortly.
Thank you very much. |
|
|
(0012677)
|
svnbot
|
2009-01-27 11:39
|
|
Repository: openbravo
Revision: 12305
Author: AinhoaPagola
Date: 2009-01-27 11:39:50 +0100 (Tue, 27 Jan 2009)
Fixes bug 0005668 Purchase Orders are created in lock status. 'Processing' column set to 'N' when inserts are done into c_order in mrp_purchaseorder function.
---
U branches/r2.40/src-db/database/model/functions/MRP_PURCHASEORDER.xml
---