Openbravo Issue Tracking System - Openbravo ERP |
View Issue Details |
|
ID | Project | Category | View Status | Date Submitted | Last Update |
0011227 | Openbravo ERP | 06. Material requirement planning (MRP) | public | 2009-11-03 11:39 | 2011-09-27 16:25 |
|
Reporter | mensenjh | |
Assigned To | jonalegriaesarte | |
Priority | normal | Severity | major | Reproducibility | always |
Status | closed | Resolution | no change required | |
Platform | | OS | 20 | OS Version | rPath Linux |
Product Version | 2.50MP8 | |
Target Version | | Fixed in Version | | |
Merge Request Status | |
Review Assigned To | |
OBNetwork customer | |
Web browser | |
Modules | Core |
Support ticket | |
Regression level | |
Regression date | |
Regression introduced in release | |
Regression introduced by commit | |
Triggers an Emergency Pack | No |
|
Summary | 0011227: MRP does not create work req on the basis of min inventory |
Description | Inventory for product A is 0. Minimum inventory is 50. There is no forecast or sales order. When the production plan is run no work requirements are created. Only when a forecast or sales order is entered does the system take into account the minimum inventory requirements. |
Steps To Reproduce | |
Proposed Solution | Production plan should calculate work requirements based on minimum stock requirements. A minimum stock requirement should be handled as a forecast or sales requirement. |
Additional Information | |
Tags | No tags attached. |
Relationships | related to | defect | 0011245 | | closed | adrianromero | Cannot process MRP Work Reqs and Material Reqs | related to | defect | 0019436 | 3.0MP9 | closed | jecharri | Manufacturing planning does not take into account safety stock as minimum requirement unless there is demand |
|
Attached Files | |
|
Issue History |
Date Modified | Username | Field | Change |
2009-11-03 11:39 | mensenjh | New Issue | |
2009-11-03 11:39 | mensenjh | Assigned To | => rafaroda |
2009-11-04 15:01 | mensenjh | Issue Monitored: mensenjh | |
2009-11-05 06:06 | rafaroda | Relationship added | related to 0011245 |
2010-02-11 18:13 | rafaroda | Assigned To | rafaroda => adrianromero |
2011-06-03 11:00 | dalsasua | Assigned To | adrianromero => dalsasua |
2011-07-20 18:11 | dalsasua | Assigned To | dalsasua => jonalegriaesarte |
2011-09-27 12:28 | gorkaion | Note Added: 0041314 | |
2011-09-27 12:28 | gorkaion | Status | new => closed |
2011-09-27 12:28 | gorkaion | Resolution | open => no change required |
2011-09-27 16:24 | psarobe | Note Deleted: 0041314 | |
2011-09-27 16:25 | psarobe | Note Added: 0041321 | |
2012-01-11 10:26 | VictorVillar | Relationship added | related to 0019436 |