ID
0004358
TypeCategorySeverityReproducibilityDate SubmittedLast Update
defect[Openbravo ERP] 06. Material requirement planning (MRP)majoralways2008-07-09 16:212008-12-15 18:45
ReporterwalleView Statuspublic 
Assigned Togorkaion 
PrioritynormalResolutionfixedFixed in Version
StatusclosedFix in branchpiFixed in SCM revision6030
ProjectionnoneETAnoneTarget Version2.40
OSLinux 32 bitDatabasePostgreSQLJava version1.5
OS VersionDebianDatabase version8.2Ant version1.6.5
Product Version2.40alpha-r3SCM revision 
Review Assigned To
Web browser
ModulesCore
Regression level
Regression date
Regression introduced in release
Regression introduced by commit
Triggers an Emergency PackNo
Summary

0004358: MRP Purchase Plan - Safety Stock Calc and Calc closed purchased orders

DescriptionHi

Two issus:

issue1: Safety Stock is calculated on each pressing of Process button





issue 2:
MRP - Purchase plan
purchase orders on which the goods entry in done are listet as "pending purchase order"
they are also still in the list when the purchase invoice is processed


Regards
Walter
Steps To ReproduceHow to recreate issue 1:


define safety stock 50 in Product -> Org Specific
Planning method with all types of Transactions
create new Purchase plan --> Process
Lines:
stock 0
minimum stock 50
sugg. purch.order 50

reprocess the same purchase plan
LInes:
stock 0
minimum stock 50
sugg. purch.order 50
sugg. purch.order 50

This means on each run you receive a additional sugg. purch. order for minimum stock





How to recreate issue 2:
sales order --> demand 1. pos 100 pieces
minimum stock 50 pieces
Planning method with all types of Transactions
MRP -> Purchase Plan -> process --> create orders
purchase order 2 pos. 100 pieces and 50 pieces
goods entry pos. with 50 pieces.

Create new salesorder demand 20 pieces

Create new MRP - purchase plan --> process
in the list of list you see still the pos. with 50 pieces open as "pending"
and so in this case the new demand of 20 pieces is not fullfilled!
TagsNo tags attached.
Attached Files

- Relationships Relation Graph ] Dependency Graph ]

-  Notes
(0008425)
svnbot (reporter)
2008-07-29 17:09

Repository: openbravo
Revision: 6030
Author: gorkaion
Date: 2008-07-29 17:09:32 +0200 (Tue, 29 Jul 2008)

Fixed bug 4358.

Modified the MRP_PurchasePlan procedure to take into account all incomings before evaluate the minimum stock.
Modified the MRP_Run_Initialize procedure to consider correctly a Purchase Order has been received using the M_MatchPo table.

---
U trunk/src-db/database/model/functions/MRP_PURCHASEPLAN.xml
U trunk/src-db/database/model/functions/MRP_RUN_INITIALIZE.xml
---

https://dev.openbravo.com/websvn/openbravo/?rev=6030&sc=1 [^]

- Issue History
Date Modified Username Field Change
2008-07-09 16:21 walle New Issue
2008-07-09 16:21 walle Assigned To => cromero
2008-07-09 16:21 walle sf_bug_id 0 => 2014215
2008-07-09 16:34 cromero Status new => scheduled
2008-07-09 16:34 cromero Assigned To cromero => gorkaion
2008-07-09 16:34 cromero fix_in_branch => trunk
2008-07-29 17:09 svnbot Checkin
2008-07-29 17:09 svnbot Note Added: 0008425
2008-07-29 17:09 svnbot Status scheduled => resolved
2008-07-29 17:09 svnbot Resolution open => fixed
2008-07-29 17:09 svnbot svn_revision => 6030
2008-09-04 16:22 psarobe Target Version => 2.40
2008-12-15 18:45 psarobe Regression testing => No
2008-12-15 18:45 psarobe Status resolved => closed